New breakwater gets the go-ahead
By Meg Olson
After
almost two years on hold, the Blaine breakwater replacement
project is set to begin in April.
We now have all the permits in hand to do the project,
said Port of Bellingham communications manager Carolyn Casey.
On November 20 the port commission gave authorization
for a consultant to develop final specifications for the
project.
The hold-up on the project was approval from the U.S. Army
Corps of Engineers, which the port applied for in January,
2000. Other permits from the city of Blaine and the state
department of fish and wildlife and department of ecology
were approved in April 2000, but the Army Corps came back
with a request for a biological assessment on top of the
original environmental assessment for the overall harbor
renovation project. The $8,000 study was completed and submitted
to the Corps of Engineers last year but the port had to
wait months before they got notice last week that the project
would have no significant environmental impact. Almost
two years later we were told there wouldnt need to
be a permit, Casey said.
After the long wait Casey said port staff are eager to get
the project rolling. Were happy, after all this
time, to get to finish the harbor improvements, she
said. The old timber breakwater at the entrance to Blaine
Harbor, over 50 years old and badly deteriorated, will be
replaced with new concrete piles and a steel wave-barrier.
Construction is scheduled to run from April 26, 2002 to
January 31, 2003, and the port anticipates selecting a contractor
in the first week of April. Realistically, it will
take the successful contractor 90 days to purchase and assemble
the new portions of the breakwater and 90 days for construction,
including demolition of the old breakwater, Casey
said.
Funding for the project got a boost November 16 from a $280,000
grant from the Interagency committee for Outdoor Recreation.
Casey said the balance of the $1.6 million dollar project
will come from cash reserves left over from the original
bond issue used for earlier harbor upgrades.
Renovations to the pier at the end of Marine Drive will
run concurrently with the breakwater replacement. Plans
are to repair sections of the deck and add lighting and
safety rails. That part of the project is paid for
out of tax dollars as a way to improve community access
to the water, Casey said.
The port plans to add further improvements to the public
pier once a lease agreement with Washington Crab is revised
and eventually build a walkway on the new breakwater for
pedestrian access.