City of Blaine to pay $20,000 extra for wastewater conveyance project

Published on Fri, Nov 18, 2011 by Jeremy Schwartz

Read More The Lighthouse Blog

Here's an early version of my story about the Blaine City Council approving $20,000 more to study a wastewater conveyance project's possible impact on migratory birds. I'm still waiting on some minor details from Blaine Public Works.


A project to convey wastewater from Semiahmoo across Blaine Harbor to the Lighthouse Point Water Reclamation Facility might end up affecting migratory birds, and the City of Blaine is going to spend about $20,000 to figure out how.

The project will use existing and yet-to-be installed sewer pipe to transfer water from the old sewer treatment plant in the Semiahmoo area of Blaine under Blaine Harbor to the Lighthouse Point facility, acting Blaine public works director Bill Bullock said. The installation of about 2,600 feet was originally scheduled for August, September and October, but encountered delays due to limited sewer pipe availability, Bullock explained.

The delays are pushing the project into November and December, which might affect migrating shore birds in the area. The city will only be allowed to continue construction if ways to reduce the effects on the birds are determined, and the city’s main contractor on the project, Wilson Engineering, needs to hire a bird biologist to do that.

Though Blaine City Council ended up approving the $20,340 amendment to the city’s contract with Wilson Engineering for the bird specialist, several council members wondered why this move had to cost just more than $20,000. Blaine community development director Michael Jones said the amount would be much cheaper than waiting until April, when the migratory season is over, to complete construction.

Jones explained the process this way: Two days of bird observation have already happened, and Jones wrote the necessary permits in such a way as to allow construction in November, but not later into the winter without determining how the area’s birds will be affected. The bird biologist Wilson Engineering hires will conduct two more days of observation, and if no negative effects on the birds are seen, construction will continue.

Further measures to protect migratory birds will be taken only if the bird specialist sees a need to, Jones explained. Based on preliminary observations, Jones said it doesn’t look like the area’s birds care much about the kind of construction Wilson Engineering is doing.

The wastewater conveyance project, with a total cost of $224,899, is part of a larger city effort to discontinue the aging Semiahmoo pump station. Once the conveyance project is complete, the city will only maintain the building on the site and return the rest of the land to the Lummi Nation.

 

 

 
Inside the Lighthouse


Welcome to the Lighthouse, the official blog of The Northern Light newspaper. The Lighthouse is the place for some breaking news, previews of upcoming articles, smaller news items and some tidbits of local information that might not make it into the print edition of The Northern Light.

The Northern Light reporter Brandy Kiger will be the main contributor to The Lighthouse, but other staff from The Northern Light may add items from time to time.

The Lighthouse is a work in progress and may undergo substantial changes as readers react to the content posted here. The Northern Light kindly asks for the patience of its readers as we edge ever so slightly into the world of blogging.

Thank you, and enjoy The Lighthouse Blog!